- Pictured is the jack and bore push pit. This operation was used to install a casing for the deep sanitary sewer that crosses 61st Ave. on the east side of Wisconsin St.
- Shown here is the casing being installed for the deep sanitary sewer crossing on the east side of Wisconsin St.
- Pictured here is the south side of the bridge over Deep River. The coffer dams are in place for the installation of the new footers. The rock berm on the east bank is for temporary erosion control.
- Paving of the temporary pavement this fall on the south side of 61st Ave. between Deep River Dr. and the bridge.
- The contractor is installing a run of storm sewer that carries water from the mainline on 61st Ave. to the detention pond south of Wisconsin St.
- Shown here is the completed detention pond approximately 1000’ south of the 61st Ave. / Wisconsin St. intersection.